Operations & Supply Chain
6.1 Industrial System (high-level):
Cryo-ethanol extraction rooms, centrifuges, chilled solvent tanks, flash evaporation, WFE, dryers, refrigeration units, utilities (steam, nitrogen, compressed air). (Reference equipment list.) SRS-CMVT-SCOPE-RELOCATION QTE-03
Engineering deliverables: labeling/tagging, inventory, disassembly/packaging, electrical redraws, re-installation procedures, commissioning checks, SCADA display adjustments, maintenance procedures. SRS-CMVT-SCOPE-RELOCATION QTE-03
6.2 Logistics & Relocation Plan:
7–8 containers from Lompoc → Port of LA → Morocco; seaworthy packaging, vacuum wrap, crating, detailed photos and packing docs; on-site coordination for unloading, sorting, tag matching; 8–10 weeks install + commissioning sprints. SRS-CMVT-SCOPE-RELOCATION QTE-03
6.3 Roles & Compliance:
Founder role in import compliance pack: DoC to IEC/UL/CE equivalents, full electrical schematics, BOM/safety components, test reports (earth continuity/insulation), user/safety manuals, serial-plate photos. Justin Calvino letter - signed …
6.4 Commercial capability (consulting/execution):
Scope: site evaluation, market strategy, equipment logistics, team/workflow design, SOPs, QA, timelines, forecasting. Botanilogix-Tiger Global Consul…
Link this page to evidence: SRS relocation quote PDF; Botanilogix–Tiger Global agreement; Justin compliance letter.